Kippax

Published on 24 March 2026 at 18:11

Drainage and footings installed in Kippax along with a reduced dig for a new storage area to the side of the house. Thanks to C.M.G for plant hire and Swiftmix for the concrete.

 

 

Preparation 

Firstly, the trees and bushes needed removing to make room for the new extension.

Footings

Once the prep work was done, the drainage could be installed and footings dug ready for concrete.

Completion

Finally the concrete could be poured to the correct levels for the following trades to take over.